Projects
Latest PSC Projects
- Gallaf Phase 2 – Functional Safety Assessment (FSA-1, -2, -3)
- Gap Analysis and Set-Up of a Functional Safety Management System (FSMS)
- HAZOP Update, SIL Verification of legacy safety systems for a gas compression station
- HAZOP, LOPA, SIL Analysis for an LNG Reloading Station
- HAZID, HAZOP for an Ammonia Import/Storage/Export Terminal
- HAZOP / LOPA of an H2-Truck Loading Station
- HAZOPs of DLR Ariane and Prometheus Rocket Test Facility
- HAZOP of a ‘Green-H2’ production and storage facility
- HAZID, HAZOP for H2- and Ammonia-supply to a copper smelting facility
- HAZOP / SIL for H2-Compressor Dry-Gas Seal System
- HAZOP, SIL for gas pipeline deodorisation facility
- Risk Analysis of plant subject to Machinery Directive for various industrial operators (acc. EN ISO 12100, 13849)
- 12 HAZOPs for SWCC Water Projects, Saudi Arabia
- Abu Dhabi Crude Oil Pipeline (ADCOP) – Follow-up HAZOP for EPC Contractor (China Petroleum Engineering & Construction Corporation)
- Crude Oil Collection Manifolds (PMAN), Petrom, Rumania – HAZOP of 34 manifolds
- Technical Audit Services for OGC, Oman – Inspection and risk-based assessment of plant condition, operation and maintenance practices at OGC Gas Supply Stations (GSS) and Pressure Limiting Stations (PLS)
Previous Projects
Project Owner: BOTAS, Turkey
Timeframe: 2001-2006
Key data about project: Total length of Turkish section: 1,070 km, diameter: 46″, 42″, 34″, design capacity: 50 Mt/a, 4 pump stations (90 MW), 1 pressure control station, terminal at Ceyhan with tank farm (7 x 150,000 m³) and jetty for 2 x 300,000 DWT tankers.
Scope: Engineering management (carried out by: Callan Consultants), responsible for pipeline and system detailed engineering and preparation of procurement packages, overall responsibility for interdisciplinary coordination of 50 company engineering staff located in four project offices and over 100 subcontractor engineers based in Ankara (300,000 man-hours), overall responsibility for quality and consistency of detailed engineering and procurement packages, comprising over 5,000 drawings and documents (including 20 procurement packages). Responsible for Home Office Support during Engineering Follow-Up phase, including preparation of Operation and Maintenance Manuals and Commissioning Procedures. Responsible for ongoing operational support including analysis of vibration issues at pump station PT1.
Project Owner: Trans-Balkan Pipeline B.V.
Timeframe: 2008 – 2010
Key data about project: FEED Design of a new 260 km, 42” crude oil pipeline to transport 50 Mta Russian and Caspian crude from the Black Sea to the Mediterranean, acting as a by-pass to the Bosporus Straits. System includes SPM unloading facility, 48“ offshore pipeline, Tank Farm and head pump station at Burgas (8×80,000m³), intermediate pump station, as well as Tank Farm (8×150,000m³), offshore pipeline and SPM loading facility at Alexandroupolis.
Scope: Engineering management, responsible for system design and optimization, as well as coordination of multi-disciplinary engineering in Home Offices.
Project Owner: Siemens KWU
Timeframe: 1997 – 2000
Key data about project: 400 MW turnkey power plant, including 270 MW gas turbine, 130 MW steam turbine, heat recovery steam generator (110, 35, 8 bar)
Scope: Acting as Employer’s Representative (carried out by: Callan Consultants) on site for Black and Veatch, responsible for monitoring Contractor construction activities and quality control of mechanical aspects of the turnkey power plant, including gas and steam turbines, heat recovery steam generator, hybrid cooling tower, balance of plant including demineralised water plant, fuel gas system, pressure vessels, station pumps and piping (including high pressure alloy steel steam pipework).
Project Owner: Watercare Services Ltd.
Key data about project: Installation of 4 x 1.7MW Jenbacher digester gas / natural gas cogeneration sets and heat recovery systems at a waste water treatment facility.
Scope: Mechanical planning (carried out by: Callan Consultants), responsible for design, specification, tendering, contract administration of biogas / natural gas engines package, plus associated power generation and heat recovery equipment. Also included in the scope of work was the upgrade of the existing digester gas compression facility and utilities, as well as installation of a new back-up natural gas supply to the site and negotiation of respective tariffs.